5. The concrete is floated to form a
level surface to build upon.
6. The inner leaf of the cavity wall is
built up to floor level.
7. Hardcore is laid to a minimum 100mm
deep and compacted to form the base of the slab.
8. A blinding screed of sand is laid
over the hardcore to prevent any sharp stones puncturing the damp proof
membrane.
9. A visquen damp proof membrane is laid
over the sand blinding and lapped onto the inner leaf of
brickwork.
10. Optional floor insulation may be
installed at this stage.
11. Concrete 100mm thick is laid to
bring the slab up to the finished floor level.
12. The concrete is floated to a smooth
level surface, suitable for tiling. Usually if you wish to lay a carpet
then a screeded floor finish or self levelling compound is added to the
floor after the conservatory is erected.
Conservatories.com - Providing you with information, advice and replacement window quote requests. Take advantage of the latest Summer Special Offers available.
Conservatories and Sunroom Portal - your guide to conservatories, sun-rooms, garden rooms and orangeries
eBuilders Ltd
1
Townsend Court, Reepham, Norfolk, NR10 4LD
Tel: 0870 850 8083 - International: +44 1603 879423 - Fax: 01603 873112
Registered in England 3404409 Please
Click Here To Contact Us
Free
Brochure & Special Offers
Looking for a new Conservatory, Sunroom or Orangery?
uPVC, Hardwood and Timber Conservatories - Fully Fitted or DIY
Nationwide Service, Sensible Prices and Reliable
Advice